Bonner Bridge on Track to Open in Late 2018, Per April 24 Update By JOY CRIST

More than two years after its groundbreaking, the Bonner Bridge Replacement project is steadily moving towards its anticipated opening to traffic later this year. At the north end of the project, crews have completed almost 75% of the northern approach. At the section that will be the bridge’s northern incline, crews are steadily driving the […]

Local News |  Full Article

Frisco Pier Operation Uses New Equipment for Piling Removal, but Project May Continue into the Fall By JOY CRIST

The contractor for the removal of the Frisco (aka Cape Hatteras) Pier has enlisted some heavy duty equipment to tackle the underwater pilings that remain close to shore, and to adapt to the rough weather that has been prevalent in the past few months. Using a large piece of equipment called a custom modified excavator […]

Local News |  Full Article