Monday, April 28, 2025

New Slash Creek Bridge in Hatteras expected to open by Memorial Day Weekend

Share post:

Slash Creek Bridge Project in March. Photo by Joy Crist.

The new Slash Creek Bridge in Hatteras Village is expected to open by Memorial Day Weekend, before the summer visitor season reaches its peak, according to an update from the North Carolina Department of Transportation (NCDOT).

“We have been delayed due to the uncharacteristically cold weather this winter, delaying some aspects of the project,” said Jonathan Rand, Public Information Officer for NCDOT. “However, we anticipate being able to have the bridge completed and open to traffic by the Memorial Day Holiday.”

Built in 1956, the original 86-foot-long bridge in the heart of the village was determined structurally deficient in an NCDOT inspection report. Structurally deficient bridges are considered safe for the time being, but have components in poor condition due to deterioration, and require significant maintenance or a full replacement to remain in service.

The project was originally included in the State Transportation Improvement Program (STIP) in 2013, and the $4.5 million endeavor was partially funded for preliminary engineering in 2015.

Hatteras Islanders got their first look at the proposed design for the new bridge at a public meeting in November 2022. The proposed replacement bridge will include two 15-foot lanes, as well as five-foot sidewalks on each side.

The contract, awarded to Smith-Rowe LLC of Mount Airy, N.C., called for construction to start no sooner than Sept. 9, 2024, and end no later than May 22, 2025.

“The concrete pile for the last end bent was driven last week, and the contractor is scheduled to pour the concrete later this week,” said Rand. “Once complete, the concrete cored slabs for span B will be set, and the contractor will begin placing the concrete barrier rail and the concrete wearing surface.”

Photo by Joy Crist.

Subcontractors have also mobilized this week and have started on the roadway portion and new drainage structures.

The concrete curb, gutter, and sidewalks will be constructed once the new drainpipe and boxes have been installed, and the final asphalt paving will immediately follow this portion of the project, with permanent pavement markings.

A detour on Eagle Pass Road will remain in place until the new bridge is open, however, visitors can still access Hatteras Village attractions and businesses with just a 1-2 minute deviation from the Eagle Pass Road detour route.

For more information on the Slash Creek Bridge project, click here.

 

Trending

Subscribe

Help Support Local News! Subscribe for Free, Upgrade to Premium, or Make a Contribution.

Related articles

Rip Current Awareness Week: The basics of rip currents

Story courtesy National Weather Service This week is Carolinas Rip Current Awareness Week, as the National Weather Service offices...

Parts of eastern North Carolina back in severe drought

From SamWalkerOBXNews.com A large band of eastern North Carolina has moved back into severe drought, as dry conditions that...

Despite a cold and snowy start to 2025, Dare occupancy and meals collections hold steady, retail sales jump 7%

From SamWalkerOBXNews.com The start of 2025 was relatively even with the previous year for Dare County hotels, vacation rentals...

All U.S. 158 lanes near Jockey’s Ridge reopen after roadway repairs completed

From SamWalkerOBXNews.com Repairs to U.S. 158 lanes northbound between Conch and Hollowell streets in Nags Head have been completed...