Buxton Beach Nourishment Update – September 28, 2017

Share post:

Buxton Beach Nourishment Update – September 28, 2017

Today, Weeks Construction crew members will begin returning to the job site and if conditions allow, pre-dredging data collection will begin.

On Friday, crews will begin moving equipment to the construction area on the beach during periods of low tide.

The hopper dredge R. N. Weeks is scheduled to arrive over the weekend and the goal is for this dredge to begin pumping sand as soon as all pre-dredging requirements are completed, including 48 hours of non-capture sea turtle trawling and inspection of the dredge in cooperation with the US Army Corps of Engineers. The hopper dredge R.N. Weeks will connect to the landing point located approximately 5,000 feet north of the first landing point, and pumping will proceed south to tie in with the section of beach that was already completed by the cutterhead dredge C.R. McCaskill.

The return date of the cutterhead dredge C.R. McCaskill will be determined once the weather pattern is more defined. Once on site, the McCaskill will resume work at the north end of the village. 

All plans are subject to change depending on sea conditions.

            

Trending

Subscribe

Help Support Local News! Subscribe for Free, Upgrade to Premium, or Make a Contribution.

Related articles

Commissioners in eight coastal counties considering resolutions opposing ferry tolls in state budget

From SamWalkerOBXNews.com Commissioners in eight coastal North Carolina counties plan to adopt a joint resolution on Monday that will...

Vehicle wreck causes Friday night power outage on Hatteras and Ocracoke Islands

A one-vehicle collision in northern Rodanthe was the cause of a power outage that affected Hatteras and Ocracoke...

Rip Current Awareness Week: Distant storms can present up close threats

Story courtesy National Weather Service This week is Carolinas Rip Current Awareness Week, as the National Weather Service offices...

NCDEQ Division of Water Resources to hold public hearing on revision to state definition of ‘wetlands’ in rule

The North Carolina Department of Environmental Quality Division of Water Resources will hold a public hearing on June...