Initial dredging work on Bonner Bridge is complete
Crews with the North Carolina Department of Transportation and the Great Lakes Dredge and Dock Company LLC Dredge Alaska completed dredging operations Sunday night at the Herbert C. Bonner Bridge on Highway12 over the Oregon Inlet.
“I want to sincerely thank all of the hardworking NCDOT crews and the dredge crews for pushing through the harsh elements to try to complete this repair work as soon as possible,” said Transportation Secretary Tony Tata. “I also want to thank the residents of the Outer Banks for their patience during this process, and our outstanding N.C. Ferry employees for all of their efforts to keep the residents connected.”
Initial scans are promising. However, it will be several days before NCDOT can determine the success of the dredging.
Approximately 30,000 cubic yards of sand were pumped during the weekend from the main navigation channel of the Oregon Inlet to the location at Bent 166 underneath the Bonner Bridge where scour, or the erosion of sand from bridge pilings, caused NCDOT to close the bridge on Tuesday, Dec. 3.
This morning, crews with NCDOT’s Location and Survey’s Unit conducted an underwater sonar survey of the area around Bent 166. Dive crews also did an initial inspection of the area to assess if the sand is compacting as it needs to in order to properly support the bridge.
To give sand time to settle and compact, NCDOT engineers are currently planning to perform another dive and sonar survey at Bent 166 on Wednesday, weather and current permitting.
NCDOT officials will then evaluate data gathered at this time to determine the overall effectiveness of the sand placement and determine the next steps for repairs.
In addition to work taking place on the support structure underneath the bridge, NCDOT is also performing a survey of the deck in the area of Bent 166 to make sure that there has not been any movement of the bridge.
Emergency Repairs
NCDOT awarded a $1.6 million contract to Carolina Bridge Company Inc. of Orangeburg, S.C. last week for emergency repairs on the Bonner Bridge.
Crews will use sandbags and four-foot tall A-Jacks to provide support to the bridge pilings and to prevent further scour from occurring. A-Jacks interlocked together will be placed around the perimeter of the support structure at Bent 166. Crews will then place sandbags inside the line of A-Jacks. An additional two layers of A-Jacks and sandbags will then be placed on top of the base layer for a total of 10-12 feet of additional protection. This will allow sand to collect over the sandbags and A-Jacks, providing additional support to the structure.
Contractor crews have begun mobilizing equipment and materials to the bridge site. NCDOT and the contractor are working together to develop a timeframe for the repairs to be complete.
In addition to the emergency repair work, Carolina Bridge Company Inc. will also begin driving two test piles later this week near the general vicinity of Bent 166. These test piles will allow NCDOT’s geotechnical staff to gather data about the load piles can carry and will help in the analysis of this situation, as well as help with future repairs.
Emergency Ferry Route
NCDOT’s Ferry Division activated its emergency route between Stumpy Point and Rodanthe with limited service the night of the bridge closure. The route went into full operation Wednesday, Dec. 4, with steady traffic and short-to-moderate wait times reported at both terminals. Dare County Emergency Management has issued a priority loading list for the route. The emergency ferry route will continue seven days a week as long as service is needed. Ferry information is available on the Ferry Division website, by calling 800-293-3779, or via Facebook (North Carolina Ferry System) and Twitter @NCDOT_Ferry).
For More Information
NCDOT will continue to update the public on this situation online and via its N.C. 12 Facebook page and N.C. 12 Twitter account.
Permanent Replacement
While NCDOT is working hard to reopen the Bonner Bridge to traffic as quickly as possible, the emergency repairs are not considered a permanent fix for the aging bridge. After 50 years of weathering many storms, the bridge needs to be replaced. In July 2011, NCDOT awarded a $215.8 million contract for the design and construction of a new bridge. Design work began immediately and construction of the new bridge was set to begin in early 2013; however, lawsuits have put the project on hold.
Read more about the history of the Bonner Bridge and the challenges to replacing this lifeline.
RELATED ARTICLES:
Governor presses environmental groups to end lawsuit at press briefing
Dare officials plan community meeting on Hatteras on bridge closure
DOT officials address Bonner safety concerns at press conference in Manteo….WITH VIDEO
Confusion, chaos, and outrage reign as DOT suddenly decides to close Bonner Bridge….WITH SLIDE SHOW
DOT has closed Bonner Bridge because of safety concerns
Governor presses environmental groups to end lawsuit at press briefing
Dare officials plan community meeting on Hatteras on bridge closure
DOT officials address Bonner safety concerns at press conference in Manteo….
Confusion, chaos, and outrage reign as DOT suddenly decides to close Bonner Bridge….
WITH SLIDE SHOW
DOT has closed Bonner Bridge because of safety concerns