Efforts Remain Focused on Overhead Solution

This media brief serves as an afternoon update to the media advisory from 9:30 this morning. Overhead Progress: Crews continue to construct the new overhead transmission line today. Lee Electrical Construction is installing the second of three cables needed for the overhead solution. New River Electrical is working to prepare the cables for connections on […]

Local News |  Full Article

Overhead Transmission Line Construction Emerges as Preferred Solution

Cape Hatteras Electric Cooperative and contract crews have simultaneously pursued two options for restoring permanent transmission service to Hatteras and Ocracoke Islands, waiting for one solution to emerge as the fastest, safest way to restore reliable transmission service. That determination has been reached. Overhead Solution: Constructing a new overhead transmission line from its underground point […]

Local News |  Full Article

Timeline for Repairs Reduced to 4-6 Days

Overhead Solution: After completing installation of the poles required for overhead transmission lines, crews worked quickly to anchor the poles, place guy wires and build the right structures to accommodate other system components. Crews will begin installing the three-phase line tonight. Concurrently, the specialist team will begin prep work for the highly technical and detailed […]

Local News |  Full Article