Pedestrian Access to Old Bonner Bridge to be Closed Starting Next Week
During the week of March 18, contractors for the N.C. Department of Transportation (NCDOT) will be installing gates and fences around the southern end of the Bonner Bridge and adjoining catwalks, as workers prepare for demolition work on the bridge. This will temporarily end public pedestrian access to the bridge while the demolition takes place over the next year.
“It’s a safety issue,” said NCDOT Division One Engineer Jerry Jennings. “The south end of the old bridge will become a work zone for the next 10-12 months, so we need to keep the public out of harm’s way.”
About 1,000 feet of the bridge will remain after the demolition process and be converted into a public walkway. That section is expected to reopen in 2020 when the demolition project is complete.
For real-time travel information, visit DriveNC.gov or follow NCDOT on social media.