New Slash Creek Bridge in Hatteras expected to open by Memorial Day Weekend

The new Slash Creek Bridge in Hatteras Village is expected to open by Memorial Day Weekend, before the summer visitor season reaches its peak, according to an update from the North Carolina Department of Transportation (NCDOT).
“We have been delayed due to the uncharacteristically cold weather this winter, delaying some aspects of the project,” said Jonathan Rand, Public Information Officer for NCDOT. “However, we anticipate being able to have the bridge completed and open to traffic by the Memorial Day Holiday.”
Built in 1956, the original 86-foot-long bridge in the heart of the village was determined structurally deficient in an NCDOT inspection report. Structurally deficient bridges are considered safe for the time being, but have components in poor condition due to deterioration, and require significant maintenance or a full replacement to remain in service.
The project was originally included in the State Transportation Improvement Program (STIP) in 2013, and the $4.5 million endeavor was partially funded for preliminary engineering in 2015.
Hatteras Islanders got their first look at the proposed design for the new bridge at a public meeting in November 2022. The proposed replacement bridge will include two 15-foot lanes, as well as five-foot sidewalks on each side.
The contract, awarded to Smith-Rowe LLC of Mount Airy, N.C., called for construction to start no sooner than Sept. 9, 2024, and end no later than May 22, 2025.
“The concrete pile for the last end bent was driven last week, and the contractor is scheduled to pour the concrete later this week,” said Rand. “Once complete, the concrete cored slabs for span B will be set, and the contractor will begin placing the concrete barrier rail and the concrete wearing surface.”

Subcontractors have also mobilized this week and have started on the roadway portion and new drainage structures.
The concrete curb, gutter, and sidewalks will be constructed once the new drainpipe and boxes have been installed, and the final asphalt paving will immediately follow this portion of the project, with permanent pavement markings.
A detour on Eagle Pass Road will remain in place until the new bridge is open, however, visitors can still access Hatteras Village attractions and businesses with just a 1-2 minute deviation from the Eagle Pass Road detour route.
For more information on the Slash Creek Bridge project, click here.